1 of 4 / Steps 1-6 Installing Joist Brackets To install you just need these simple tools and materials
1 Make sure your ledger board (main support board attached to house) is properly secured and flashed. There should be a minimum of 8” of flashing out from ledger board (FIG.1-A) . If flashing does not extend past the gap between the first two deck boards, install gutter along ledger board after DrySnap system is installed.
2 Mark your chalk line nearest the ledger board. Measure 3-1/2” out from the ledger board on opposite sides of deck, and pop or snap chalk line (FIG.1-B). This mark will be your “center” mark for positioning the joist brackets.
3 Mark your outermost chalk line. Measure 3-1/2” out from the beam on opposite sides of deck and pop or snap chalk line (FIG.1-C). This mark will be your “center” mark for positioning the joist brackets.
4 Proceed to snap the middle chalk lines. Beginning with the ledger board side, measure, mark & snap chalk lines every 20” apart (FIG.1-D). Again, this mark will be your “center” mark for positioning the joist brackets. Spacing between rows should not exceed 20”, including the last row.
5 Before installing joist brackets, place a level on the joist in several locations to make sure deck is level or pitched toward drainage direction of system. (Inconsistent or bowed joist are covered later in these instructions.)